A dryer’s air dew point and the moisture in dried pellets answer different questions. Record both if they are part of the acceptance agreement, but use a pellet measurement to assess a pellet-moisture requirement. Novatec explains why a dryer output reading alone does not establish resin readiness.
For PET or another hygroscopic resin, start with the exact grade supplier’s current technical data and your process requirements. Agree on the limit, unit, test method, sampling points and equipment scope before the trial. There is no single PET moisture setpoint that this guide can substitute for those documents.
Agree on the acceptance test
Identify the resin grade, lot, initial condition and intended production rate. Define the hopper fill, drying temperature, residence time, airflow, conveying cycle and operating duty to be witnessed. Agree when the system is stable and how long it must run at that condition. Record the dryer’s displayed dew point and where it is measured, along with actual temperatures, load and any alarms or interruptions.
Take paired samples from the hopper discharge and an established, authorized sampling location at the actual point of use, such as a safe machine-feed sampling port, under the same agreed duty. A pellet takes time to travel through the system: agree on the transport lag and sampling sequence so that the samples represent the same material passage as closely as practicable. Record times, locations and the method used to establish that relationship. Avoid claiming a matched pair if it cannot be established.
Use the agreed sampling procedure to minimize exposure and contamination; seal, label and transfer samples promptly. Record the containers, delay before testing and laboratory or instrument used. Agree on a method appropriate to the grade and contract: ASTM D6869 covers a Karl Fischer reaction method for moisture in plastics, while ASTM D6980 covers a loss-on-drying method. Loss on drying is not automatically all water, and results from different methods or instruments should not be treated as interchangeable without validation.
Record the evidence and scope
The example below uses an invented limit of 100 ppm by mass, solely to show how a record can support different decisions. It is not a PET recommendation. Both readings use the same agreed method and unit; the paired sampling and stable duty have been documented.
| Acceptance item | Illustrative result | Decision to record |
|---|---|---|
| Dryer air dew point | Meets the separately agreed air criterion | Record the witnessed air item; it does not establish pellet moisture. |
| Hopper-discharge pellets | 80 ppm versus 100 ppm limit | The discharge sample meets this illustrative pellet limit. |
| Point-of-use pellets | 140 ppm versus 100 ppm limit | The point-of-use sample exceeds the limit; hold that acceptance item and investigate. |
If the dryer supplier’s contract ends at hopper discharge, the witnessed discharge result can support that specified item while the point-of-use item remains open for the party responsible for conveying and use. If one supplier owns the complete system through the machine feed point, the point-of-use requirement remains open within that scope. Record partial signoff only where the contract permits it; a sample result alone does not settle every equipment or production requirement.
Repeat before assigning a cause
Check the sample identification, timing, sealing, instrument method and calibration, then repeat paired measurements under the agreed duty. Inspect transfer and conveying conditions with the responsible parties. A difference between the two measurements is a reason to investigate, not proof of where or why moisture changed. Document the repeat results and any agreed corrective action before closing the open item.
Attach the grade requirement, test procedure, raw readings, operating log and signed scope to the acceptance record. For sizing and technology selection, see hopper dryer sizing and hot-air vs desiccant dryers. The RFQ checklist helps define the supply boundary. Browse Novatec and Conair for supplier starting points.